Towards the end of 2022, with most of the parts for the mainline safety systems in hand, but with the workshops at Barrow Hill at full capacity, the decision was taken to move the locomotive to the UK Rail Leasing works at Loughborough for the mainline equipment installation to take place. The move by road from was made from Barrow Hill to Loughborough on 24/11/2022 - with traction motors still missing from the locomotive a move by rail was not possible. A series of photographs shows the locomotive being loaded and moved at Barrow Hill by Allelys Heavy Haulage.